Garage Project
September 4, 2004 - Winter 20074 Phase Project
Phase 1 - Electrical
September 4, 2004 - September 6 2004
1 - 100 Sub-panel with 4 20 Amp Breakers
2 - 100 Watt Garage Attic Lights - own circuit
2 - 40 Watt Wall mounted Flour. Lights - own circuit
4 - 40 Watt Ceiling mounted Flour. Lights - own circuit
9 - 20 Amp Outlets on 3 walls and ceiling
![]()
![]()
![]()
![]()
Phase 2
Completed April 2005
Insulation: R19 in ceilings & R11 in walls
Drywall: Ceiling & upper 4 feet of wall
Paint: "Phantom Lake" by JC Licht
Shelving in attic not pictured
![]()
![]()
Phase 3
Completed Spring 2006
Dug and buried 220v line - 8 gauge 50amp circuit - 120' pull
Wood Paneling up (done expertly by Danny & Ryan)
Sealed all Wood Paneling after winter
Cedar Baseboard & Shelving sealed and installedhaving the wood paneling completely removable has come in very handy and I would highly recommend this type of wall finishing be done because it aids in cleaning and or adding electric (ie for the garage heater, which was installed winter '07)
![]()